REM Edouard-Montpetit Station – Digging 20 storeys underground

Edouard-Montpetit-station-digging-January-2019-min

It is a massive undertaking. In order to build the REM’s Edouard-Montpetit station, workers first have to dig down to the metro’s blue line and then to the tunnel under Mount-Royal – the equivalent of at least 20 storeys. They refer to it as a ‘surgical operation, as they have to dig through a very hard, densely built sector of bedrock. And it is no easy task.

REM Edouard-Montpetit Station

Because of the challenges involved, they chose a method of ‘controlled blasting’. It is technique involving the use of small explosives to slowly break up the layers of bedrock. Cranes then collect all the rock cuttings and put them into load bearing trucks to be taken away. They hired some of the best experts in the field to define the drilling and blasting parameters and methods, including Pierre Groleau, a mining engineer and explosives expert for NouvLR. He has worked on projects in many countries, as well as on urban construction sites and ‘large-scale mega surface, underground and underwater’ projects. According to Groleau, ‘the challenge and complexity of the  Edouard-Montpetit site is based on its proximity to homes, schools and utilities’ and ‘the type of activity must take these important considerations into account to manage vibrations and rock projections during controlled blasting’.

Controlled blasting edouard montpetit – REM

Special measures are always used to ensure the safety of not only the workers, but also the public and surrounding infrastructure – and planning everything is taken very seriously. They do a ‘soil characterization’ (to determine the nature and extent of any contamination in the soil) and use line drilling and ‘compartmentalized blasting’ in order to reduce the vibrations felt during the work. Each blast is monitored by seismographs placed around the site and they cover the area with layers of ‘blasting mats’ with a ‘dual layer of geotextile membrane’ in order to control any flying rocks or stones.

Edouard-Montpetit station blast -REM

Taking it even a step further, they are only using the best products available. High-precision electronic detonators are used, enabling them to check the ignition sequence of a blast in order to identify, locate and correct any mistakes before proceeding. Once completed, the station will be the second-deepest in North America at 70 meters, with the Washington Park light rail station located in Portland, Oregon being the deepest at 79 metres. The whole operation to excavate the main shaft at Edouard-Montpetit began in October of 2018 and they are soon ready for the next step – to build the underground REM station, scheduled to open in 2022. And as they say, what you see of the site at surface level is ‘only the tip of a highly complex iceberg’.

Once in operation, travel times from the station to different parts of the REM’s four lines will be as follows: McGill (green line) 3 minutes, Bonaventure-Gare Centrale (orange line) 4 minutes, Station A40 (Mascouche line) 6 minutes, Montreal-Trudeau Airport 16 minutes, Dix-30 Brossard 17 minutes, Kirkland, 26 minutes and Deux-Montagnes 29 minutes. You can watch a short video of a blast.

By: Bonnie Wurst – info@mtltimes.ca

Other articles:

REM project seeing light at the end of the ‘track’

Will REM trains and schedules be reliable?

Montreal Metro System to REM and the Future

Technology Should Disappear, Not Dominate: A More Considered Approach to Luxury Real Estate in Marbella

Evolving luxury landscape, discerning buyers are no longer searching through endless listings – they are seeking clarity, discretion, and alignment with their lifestyle. This shift is precisely where Constans Group positions itself, offering a refined, client-centric approach to discovering exceptional opportunities in real estate Marbella, including some of the most sought-after luxury villas for sale

Behind The Moon play premieres in Montreal

Behind the Moon Reveals Dark Side of the Canadian Immigrant Experience

MONTREAL, April 10, 2026 — What begins as a chance encounter between an employee of a South Asian restaurant in Toronto and a taxi driver who arrives at closing time because he craves some Indian food turns into an expose that delves into the ugly side of the current wave of the immigrant experience in Canada.

Employer Branding in an Era of Digital Transparency

Employer Branding in an Era of Digital Transparency

Digital transparency transforms how organizations are perceived, especially in the context of talent attraction and retention. Public platforms and employee-generated content make internal culture a visible signal to job seekers. As the boundaries between internal experience and external reputation blur, credibility has become a critical differentiator for employers. Employer branding now unfolds in public view,

Harlem Globetrotters celebrate 100th in Montreal

Harlem Globetrotters 100th Tour Tips Off in Montreal and Laval

Tickets are still available to catch the Harlem Globetrotters’ 100 Year Tour, as it presents two games in the city: on April 17 at the Bell Centre, and April 18 at Place Bell in Laval. Holders of more than 60 Guinness World Records, the clown princes of basketball celebrate their centennial year with plenty of

Monty Python Legend to return Montreal this Fall

For the first time in 17 years, legendary Monty Python member/writer/producer/lecturer (and silly walk advocate) John Cleese returns to Montreal to prove to his legion of local fans that he is still alive and well, which explains why he has called his new tour “Not Dead Yet!”, and makes a one night only stop at